PLANNING
The deadlines for the deliveries of Lot 1 were established on the contract starting from the start date (November 12, 2019). Due to the global pandemic of Covid-19, Kiswire Andvanced Technology, Ltd presented a request to extend the contract. The request was accepted by ENEA. The new delivery schedule as amended after the extension, is as follows:
Delivery |
Description |
Date of the delivery |
Completed |
A |
3 Tons of strand |
21/07/2020 |
|
B |
7 Tons of strand |
27/10/2020 |
|
C |
6 Tons of strand |
20/12/2020 |
|
D |
7 Tons of strand |
04/05/2021 |
|
E |
6 Tons of strand |
13/07/2021 |
|
F |
7 Tons of strand |
28/09/2021 |
|
G |
6 Tons of strand |
23/11/2021 |
|
H |
7 Tons of trand |
04/01/2022 |
|
I |
6 Tons of strand |
15/02/2022 |
|
Doc 2 |
Final Report |
22/02/2022 |